3rd Round Results - Announced April 27, 2016

Segment 1. Residential & Small Commercial (50 kW and below):

  • 3 bids were received, totaling 116.5 kW
  • 2 awards were made, totaling 78.1 kW
  • One bid was rejected because pricing was found not to be competitive
  • The average price per SREC in Segment 1 was $239.66.

Segment 2. Residential & Small Commercial (Greater than 50 kW to 2 MW):

  • Ten bids were received, totaling 5,022.40 kW
  • Ten awards were made, totaling 5,022.40 kW
  • No bids were rejected
  • The average price per SREC in Segment 2 was $229.82

Segment 3. Subsection t. landfills, Brownfields, or Areas of Historic Fill (Up to 5.2 MW):

  • No bids were received 

2nd Round Results - Announced December 17, 2015

Segment 1. Residential & Small Commercial (50 kW and below):

 

  • 13 bids were received, totaling 248.91 kW
  • 11 awards were made, totaling 235.51 kW
  • Two bids were rejected because pricing was found not to be competitive
  • The average price per SREC in Segment 1 was $256.89

 

Segment 2. Residential & Small Commercial (Greater than 50 kW to 2 MW):

  • Seven bids were received, totaling 3,219.7 kW • Seven awards were made, totaling 3,219.7 kW
  • No bids were rejected
  • The average price per SREC in Segment 2 was $227.29

Segment 3. Subsection t. landfills, Brownfields, or Areas of Historic Fill (Up to 5.2 MW):

  • No bids were received 

 

1st Round Results - Announced July 22, 2015*

Click here to view the Board Order​ On Results of First Solicitation


ReceivedAwarde​d
NumberAmount (kW)NumberAmount (kW)
All Segments/EDCs9          1,246.6 8     1,231.76
ACE - Segment 13             85.5 2          70.68
ACE - Segment 25           374.5 5374.48
JCP&L - Segment 10000
JCP&L - Segment 21786.61786.6
RECO - Segment 10000
RECO - Segment 20000
RECO - Segment 30000